- Steel
- 100+ T
- Geometry
- Curved in plan
- Tested
- In-house assembly test
- Sector
- Material handling
- Status
- Delivered
The project
A pipe conveyor turns where a belt cannot, so its galleries curve: every truss is different.
What we made
- Curved truss galleries
- Painting
- In-house assembly test
How we built it
- Robotic H-beam cutting and bevelling cellMembers cut and coped by robot.
- Conveyor shot-blasting lineBlasted and painted in house.
Assembled and checked in our works, then shipped.
More case studies
Oil & gas · Louisiana, USA
Enclosed ground flares for an LNG export terminal in Louisiana
4 chambers, 2,200+ T, for an LNG export terminal
Oil & gas · Hazira, Gujarat
A 50 m enclosed ground flare chamber, delivered in 3 months
50 m high, 200+ T, delivered in 3 months
Oil & gas · USA
A 35 m flare riser with its liquid seal
A 35 m riser with its liquid seal, tip and access
Oil & gas · Louisiana, USA
Enclosed ground flares for an LNG export terminal in Louisiana
4 chambers, 2,200+ T, for an LNG export terminal
Oil & gas · Hazira, Gujarat
A 50 m enclosed ground flare chamber, delivered in 3 months
50 m high, 200+ T, delivered in 3 months
Oil & gas · USA
A 35 m flare riser with its liquid seal
A 35 m riser with its liquid seal, tip and access
Start a project
Send us a drawing
A project like this?
Send the drawings and an engineer will tell you how we would build it.